IrelandStatus

Ireland Work Permit and IRP Processing Dates: September 2026

IrelandStatus reads the official DETE page every 6 hours and the official Immigration Service Delivery page every Friday at 12:00 UTC. This report sets out each processing date as read in September 2026. It describes the queues as a whole, not any one application, and is not a prediction.

Work permits (DETE)

Work permits (DETE): read on 17 of 30 days in September 2026.

Between 1 and 17 September, as read from the official page:

  • Critical Skills Employment Permit moved forward 10 days (24 August 2026 to 3 September 2026)
  • General Employment Permit (New) moved forward 13 days (24 July 2026 to 6 August 2026)
  • Other New Applications did not move (21 July 2026)
  • Intra-Company Transfer (New) moved forward 32 days (7 August 2026 to 8 September 2026)
  • Intra-Company Transfer (Renewal) moved forward 20 days (3 June 2026 to 23 June 2026)
  • Renewal Applications moved forward 19 days (3 June 2026 to 22 June 2026)
  • Reviews / Appeals did not move (24 January 2026)

There were no readings from 18 to 30 September.

Work permits (DETE), September 2026: the first and last value of each permit type, how far it moved, and notes
Permit typeFirst valueLast valueMovement and notes
Critical Skills Employment Permit24 August 2026on 1 September3 September 2026last read on 17 SeptemberMoved forward 10 days
  • No readings from 18 to 30 September; when readings resumed on 1 October, the date was 23 September 2026
General Employment Permit (New)24 July 2026on 1 September6 August 2026last read on 17 SeptemberMoved forward 13 days
  • No readings from 18 to 30 September; when readings resumed on 1 October, the date was 25 August 2026
Other New Applications21 July 2026on 1 September21 July 2026last read on 17 SeptemberDid not move
  • No readings from 18 to 30 September; when readings resumed on 1 October, the date was 13 August 2026
Intra-Company Transfer (New)7 August 2026on 1 September8 September 2026last read on 17 SeptemberMoved forward 32 days
  • No readings from 18 to 30 September; when readings resumed on 1 October, the date was 29 September 2026
Intra-Company Transfer (Renewal)3 June 2026on 1 September23 June 2026last read on 17 SeptemberMoved forward 20 days
  • No readings from 18 to 30 September; when readings resumed on 1 October, the date was 13 July 2026
Renewal Applications3 June 2026on 1 September22 June 2026last read on 17 SeptemberMoved forward 19 days
  • No readings from 18 to 30 September; when readings resumed on 1 October, the date was 8 July 2026
Reviews / Appeals24 January 2026on 1 September24 January 2026last read on 17 SeptemberDid not move
  • No readings from 18 to 30 September; when readings resumed on 1 October, the date was 14 April 2026

Dates here are when a value was first read from the official page. IrelandStatus publishes a change only after a second reading agrees, and some changes were held for review, so a category's history table can show a later date for the same change.

IrelandStatus did not publish changes from 27 July to 15 September 2026. The dates for this period are as read from the official page.

Official source: enterprise.gov.ie →

IRP renewals (ISD)

IRP renewals (ISD): no readings in September 2026.

IRP renewals (ISD), September 2026: the first and last value of each stamp, how far it moved, and notes
StampFirst valueLast valueMovement and notes
Stamp 1 & 1HNoneNone
  • No readings this month; before that, last read on 24 July: 9 July 2026; when readings resumed on 6 October, the date was 12 August 2026
Stamp 1GNoneNone
  • No readings this month; before that, last read on 24 July: 20 April 2026; when readings resumed on 6 October, the date was 10 August 2026
Stamp 2, 2A & 1ANoneNone
  • No readings this month; before that, last read on 24 July: 25 April 2026; when readings resumed on 6 October, the date was 12 August 2026
Stamp 4NoneNone
  • No readings this month; before that, last read on 24 July: 14 March 2026; when readings resumed on 6 October, the date was 28 August 2026
All Other StampsNoneNone
  • No readings this month; before that, last read on 24 July: 28 April 2026; when readings resumed on 6 October, the date was 8 September 2026

Dates here are when a value was first read from the official page. IrelandStatus publishes a change only after a second reading agrees, and some changes were held for review, so a category's history table can show a later date for the same change.

Official source: irishimmigration.ie →

Get a free email when a processing date changes

To cite this page: IrelandStatus, “Ireland Work Permit and IRP Processing Dates: September 2026”, https://irelandstatus.com/reports/2026-09. Official sources: https://enterprise.gov.ie/en/What-We-Do/Workplace-and-Skills/Employment-Permits/Current-Application-Processing-Dates/ and https://www.irishimmigration.ie/registering-your-immigration-permission/how-to-renew-your-current-permission/renewing-your-registration-permission-if-you-live-in-the-republic-of-ireland/